Can Your School Support an Esports Program? A Practical Readiness Assessment

By Austin Miller, Esport Supply

When a school contacts us about starting an esports program, I usually have a few questions before we get into gaming computers, furniture, or facility design. Who’s going to run the program? Has the money been approved? Where will the space be located, and has anyone from campus IT looked at it?

A school is usually ready to move forward when someone is responsible for the program, funding has been approved, and the university has a suitable location with IT involved in planning. It also needs to know how students will use the facility and who will manage it after opening. Most schools have a pretty good idea of what they’d like to build, but some still have work to do before they’re ready to start.

Who’s Going to Run the Program?

One of my first questions is who’s managing the space and which department is paying for it. Those aren’t always the same people. Depending on the school, the program might fall under athletics, student activities, or another department, and each handles purchasing and operations differently.

Someone needs to be responsible for scheduling, student access, supervision, and working with other campus departments. I also want to understand the purchasing process, because university procurement can take time. If the school has a target opening date but hasn’t figured out who can approve purchases or sign off on construction, that can delay the project.

Has the University Approved the Budget?

There’s a difference between a university wanting an esports facility and having the money committed to build it.

We worked with a university that wanted to turn an old student newspaper office into a 12-station gaming room by spring semester. The space had its own entrance, existing card access, and needed very little construction. But during our initial conversations, we learned that the school still had to present a roughly $200,000 proposal to its Chancellor and potential donors.

Until the funding is approved, it’s difficult to establish a reliable purchasing schedule or construction timeline. I’ve seen schools start discussing equipment before they’ve worked out how they’re going to pay for the project.

I also ask whether they’ve considered expenses after opening. Schools usually budget for PCs and furniture, but annual software renewals, game licenses, maintenance, and hardware replacement can get overlooked. Gaming computers may need a substantial refresh after five or six years, and hardware prices can change during that time. We’ve covered those expenses in our article on how universities fund esports programs and facilities.

Is the Location Going to Work?

Schools often start with whatever room happens to be available. Sometimes it’s an old office, a basement, or a space that hasn’t been used in years. That doesn’t automatically make it a bad choice, but I want to know more about the location before we start planning around it.

Will students see the facility and know it’s there? Can they access it after regular campus hours? Is there enough electrical capacity for dozens of gaming computers? Noise is another consideration, especially if the room is next to classrooms or offices.

At the University of Oklahoma, we evaluated several locations with the university and Crawford Architects before selecting an empty retail storefront on campus. The location sits along a street used by an estimated 45,000 to 60,000 fans during home football games. That visibility made it a good fit for a program looking to become a bigger part of campus life.

Has Campus IT Looked at the Space?

This is probably the issue schools underestimate most often. A room can have plenty of electrical outlets and still need substantial work before it’s ready for gaming computers. We’ve encountered spaces requiring new cabling to support gigabit connections, separate VLANs for gaming traffic, or network ports that hadn’t been activated.

The university planning the 12-station room had some of these problems. Existing conduit made it difficult to bring fiber into the space, and there wasn’t a designated location for the server rack or a plan for battery backup during power outages. We’ve covered network and internet requirements for esports facilities in more detail for schools planning a new space.

EDUCAUSE’s guidance on implementing collegiate esports programs also discusses involving IT and facilities staff during planning. I want those departments involved early because they can identify work that affects the cost and opening date.

How Will Students Use the Facility?

I ask whether the school is planning varsity competition, club gaming, recreational use, classes, or a combination of those activities. That helps us understand how many stations the school needs, whether there will be dedicated team areas, and how the facility should operate.

If the university wants to stream competitions, charge students for gaming sessions, or allow students to bring their own equipment, we need to know during planning. Those decisions affect staffing, software, scheduling, and equipment purchases. Sometimes starting with a smaller program makes more sense than committing to a large facility immediately.

What Does a School That’s Ready Look Like?

The University of Oklahoma is a good example of a school that worked through these questions and built its program in stages. Michael “Moog” Aguilar, OU’s Director of Esports & Co-Curricular Innovation, presented the idea of converting the retail storefront in fall 2022. The university secured the space in early 2023, received renovation approval that June, and gave students a preview that fall. The full venue opened in August 2024.

We worked with OU and Crawford Architects on a roughly 4,500-square-foot facility with gaming stations, team rooms, an arcade, and production space. The first phase included 40 PCs, three VR stations, racing rigs, and consoles, which we installed in two workdays. According to the project figures we have, the program serves approximately 4,900 community members and 150 competitive players, and the university continues adding equipment.

What impressed me about Oklahoma was how much work Moog and the university had done before construction started. He’d made the case for the program, the administration supported the project, and they had a location that made sense. They also planned the facility so they could add equipment as the program grew.

Oklahoma’s project took time, but the university had a plan for getting it done. That’s something I encourage schools to think about early. A facility doesn’t have to open with every feature the program might eventually need. It does need people who can make decisions, a realistic budget, and a space the university can maintain.